Nama Electricity Distribution told Oman's state news agency which named substations in Muscat Governorate — including one serving the Rusayl Industrial zone — are already complete or under way under its 2026 investment plan, giving a dated, place-specific reference point for checking grid headroom before a new connection or expansion.
- Geography
- Oman
- Sector
- Electricity distribution infrastructure, industrial and commercial facilities
- Theme
- Energy, Water & Resource Efficiency
What happened
On 22 November 2026, Nama Electricity Distribution Company told the Oman News Agency that its 2026 investment plan for developmental and investment projects across Muscat Governorate has a planned budget of 22.47 million OMR [1], covering medium-voltage (33 kV) and (11/0.415 kV) networks and grid-reinforcement works. Eng. Mohammed Rashid Al Qari, the company's General Manager of Major Projects, said actual spending from January to August 2026 reached 10.79 million OMR [1]. Among the projects he named as complete is the Rusayl Industrial 1 substation, a 2×20 MVA facility that cost about 1.29 million OMR [1], alongside several other named substation and feeder upgrades across the governorate's wilayats.
Why it matters
For operations and facilities managers planning a new connection or expansion in Muscat Governorate, this is a confirmed, dated disclosure of which specific grid-capacity additions — not only an aggregate national investment figure — are already complete or under way in named areas, including an industrial zone. It gives a reference point for checking grid headroom and connection timing with Nama Electricity Distribution directly, rather than relying on a general statement that network investment is increasing.
Limitations
The figures are the company's own statement to the Oman News Agency, not an independently audited capital-expenditure report, and the article gives no expected completion date for projects still under construction. Only Muscat Governorate is covered, and the figures do not state the spare capacity a named substation, including the one serving Rusayl Industrial, has available for a new connection — a site would still need to confirm that directly with Nama Electricity Distribution.
BARZ